Shell Pierce C1 Development

 

CONDUCTOR PILE INSTALLATION

OFFSHORE WEST MALAYSIA (2007)

Talisman Malaysia Ltd used a Dawson Construction Plant hammer to drive 4off 36” conductor piles at there Global Industries,
s DB Seminole Rig.

A Dawsons HPH9000 hydraulic piling hammer was used to drive 140m piles, 74m below the mud line.

Talisman Energy Inc. is a global, diversified, upstream oil and gas company, headquartered in Canada. Talisman’s three main operating areas are North America, the North Sea and Southeast Asia. The Company also has a portfolio of international exploration opportunities.

Talisman Malaysia had used Dawson piling hammers successfully on numerous wells / leases around the offshore West Malaysia region.

DATE / LOCATION LEASE / WELL
06-04-2002 / Offshore West Malaysia / West Bunga Raya - 1
29-04-2002 / Offshore West Malaysia / South Bunga Seroja - 1
01-05-2002 / Offshore West Malaysia / North Bunga Cengkeh - 1
16-04-2003 / Offshore West Malaysia / North Bunga Pakma - 2
02-09-2003 / Offshore West Malaysia / North Bunga Orkid - 1
11-11-2003 / Offshore West Malaysia / Bunga Tanjung - 1
21-12-2003 / Offshore West Malaysia / Bunga Tulip - 1
13-07-2004 / Offshore West Malaysia / North-West Besar - 1

 

Technical Specifications

PILE SIZE - 36” , 1” WT
PILE LENGTH - SEE BELOW
---------------------------------------
HAMMER TYPE - HPH9000
RAM WEIGHT - 4,750kg
IMPACT VELOCITY - 6.0m/s
MAXIMUM PILE ENERGY - 35KNm
MINIMUM PILE ENERGY - 35KNm
BLOW RATE - 60-90bpm
BODY DIAMETER - 750mm
TOTAL WEIGHT - 13,500mm